How to Participate
Energy and Environment Committee
2
Exemption, Board of Water and Power Commissioners and City Attorney reports, and Ordinance relative to updating regulatory programs and adding new types of environmental energy and renewable energy credit products available for purchase, sale, and exchange.
The amendments are necessary due to changes in federal, state, and local environmental regulations since the code was last updated in 2014
3
Exemption, Board of Water and Power Commissioners and City Attorney reports, and Ordinance relative to the Large Power Transformers and Variable Shunt Reactors for Various Substations Project.
This deviates from the traditional lowest-bidder approach due to the highly specialized and complex nature of the equipment, which includes custom eng...
5
City Clerk annual report relative to the Bradley Landfill Community Trust Fund for Fiscal Year 2023-24.
The fund began the fiscal year with a balance of $418,511.49
6
Motion (Nazarian - Hutt) relative to the status of the Hydration Station Initiative Program, and related matters.
The program aims to expand public access to drinking water, reduce single-use plastic bottle consumption, and promote healthier alternatives to sugary...
8
Board of Water and Power Commissioners report relative to the Second Amendment to an agreement with Black and Veatch Corporation for the North Haiwee Dam Seismic Improvement Project.
The amendment extends the contract term by an additional three years, from its original expiration of February 3, 2026, to February 2029
9
Exemption, Board of Water and Power Commissioners and City Attorney reports, and Ordinance relative to the use of the competitive sealed bid proposal method for the award of one or more contracts to accelerate the implementation of the Plug into Power: Community Distributed Energy Resources Project.
The contracts can have a term of up to ten years
10
Exemption, Board of Water and Power Commissioners and City Attorney reports, and Ordinance relative to the utilization of an alternative project delivery method on a competitive sealed proposal basis and approval of project delivery criteria for the Encino Reservoir Floating Pilot Project.
This method allows LADWP to contract with a single firm responsible for all design, procurement, and construction phases, which is deemed advantageous...