Skip to main content
26-442A
CONSENT AGENDA
Active
1 appearance

Authorize a one-year service price agreement for excavation, removal, and disposal of residual solids from Lagoon No. 1 at Bachman Water Treatment Plant for the Dallas Water Utilities Department - American Process Group LLC, most advantageous proposer of three - Estimated amount of $4,798,076.97 - Financing: Dallas Water Utilities Fund

City: Dallas, TX
First Seen: February 25, 2026
Latest Activity: February 25, 2026
contractsutilities

Summary

This resolution authorizes the City Manager to execute a one-year service price agreement with American Process Group LLC for the excavation, removal, and disposal of residual solids from Lagoon No. 1 at the Bachman Water Treatment Plant. The estimated cost for this service is $4,798,076.97, to be funded by the Dallas Water Utilities Fund. The agreement includes an option for a six-month extension at the City Manager's discretion. Payments will be based on services directed and performed by the contractor.

This contract ensures the continued operation of the Bachman Water Treatment Plant by managing waste solids, which is essential for providing safe and reliable drinking water to Dallas residents. The cost is covered by the Dallas Water Utilities Fund, meaning no direct tax increase for this specific service.

high

Legislative Journey