0145-26
Resolution
Active
3 appearances

A Resolution authorizing the Mayor or her designee, on behalf of the Urban County Government, to execute Change Order No. 2 to the Agreement with Terracon, for Special Inspections associated with the new Senior and Therapeutic Center construction, increasing the Contract price by the sum of $13,870, from $50,305 to $64,175. [Dept. of General Services, Ford]

City: Lexington, KY
First Seen: February 24, 2026
Latest Activity: February 26, 2026
budgetcontracts

Summary

This resolution authorizes the Mayor or her designee to execute Change Order No. 2 with Terracon for Special Inspections related to the New Senior and Therapeutic Center construction. This change order increases the contract price by $13,870.00, bringing the total contract amount from $50,305.00 to $64,175.00. The increase is necessary due to additional soil density testing requirements.

Financial Details:

  • Original Contract Amount: $50,305.00
  • Increase via Change Order No. 2: $13,870.00
  • New Total Contract Amount: $64,175.00
  • Funds are budgeted from Fund 2615-606102-6051-90511-2025-SRTHER_CTR_2025_CONSTRUCT_CAP.