Award a Construction Contract to 2C Land and Timber Management Corp of Roseville, CA for Phase II of the Lake Berryessa Resort Improvement District Wastewater Ponds Groundwater Inflow Mitigation Project, LB 18-02; and approve Amendment No. 3 to Agreement No. 240306B with GHD, Inc. adding construction administration and inspection services for the project and increasing compensation from $312,570 to $441,649. (Fiscal Impact: $933,009 Expense; Lake Berryessa Resort Improvement District Fund; Budgeted; Discretionary)
Summary
The City Council is set to award a construction contract to 2C Land and Timber Management Corp of Roseville, CA, for Phase II of the Lake Berryessa Resort Improvement District Wastewater Ponds Groundwater Inflow Mitigation Project (LB 18-02). The bid received from 2C Land and Timber Management Corp was $803,930.00, making it the lowest responsive bid among the 14 submitted.
Additionally, the council will approve Amendment No. 3 to Agreement No. 240306B with GHD, Inc. This amendment adds construction administration and inspection services for the project and increases GHD, Inc.'s compensation from $312,570 to $441,649. The total fiscal impact for this item is an expense of $933,009, to be funded from the Lake Berryessa Resort Improvement District Fund, which is budgeted for this purpose.
The total project budget, including Phase I actuals, Phase II budget, and allowances, is $1,544,544. The Clean Water State Revolving Fund (Project C-06-8477-1110) is the funding source for this Groundwater Inflow Mitigation Project.