2026-77
ACT - Bond Act
Active
6 appearances

BOND ACT-RGP15-General Infrastructure-Fuel Tank Replacement '24-'28

City: West Chester, PA
First Seen: February 9, 2026
Latest Activity: March 2, 2026
budgetenvironmentutilities

Summary

This Bond Act authorizes the County of Westchester to issue $800,000 in bonds to finance the replacement of fuel tanks and related infrastructure for the Department of Parks, Recreation & Conservation. The project, designated RGP15, will cover fuel tank systems at Tibbetts Brook Park, Glen Island Park, Maple Moor Golf Course, and other County Parks.

Key Aspects:

  • Purpose: To ensure public safety, regulatory compliance, operational reliability, and environmental protection.
  • Scope: Includes design, construction, and management for removal/replacement of fuel storage tanks, piping, equipment, and site work.
  • Timeline: Design is estimated to take six months, followed by an eight-month construction period after contract awards.
  • Environmental Review: Classified as a Type II action under SEQR, meaning no further environmental review is required.
  • Fiscal Impact: The bond issuance will result in an anticipated annual cost of $46,935 for principal and interest over a 30-year period.