Infrastructure & Housing
1.
BOND ACT(Amended)-RBR07-Bronx River Pathway Reconstruction
The total authorized amount is now $11,130,000, an increase of $1,700,000 from the previously authorized $9,430,000
2.
CBA-RP056-Playland Infrastructure, Rides and Site Work
Following an arbitration decision, the County owes Standard Amusements LLC $519,294 in remaining interest on liquidated damages
3.
2025 Operating Budget Amendment-RP056-Playland Infrastructure, Rides and Site Work
The amendment reduces capital costs by $27,710,000 and adds interest costs of $519,294, resulting in a net decrease in General Fund expenses and reven...
4.
BOND ACT(Amended)-RP056-Playland Infrastructure, Rides and Site Work
The total estimated maximum cost has been increased from $36,000,000 to $36,519,294
1.
HON. MARGARET A. CUNZIO - Request for Removal from the WC Saw Mill Sanitary Sewer District - 621 Chappaqua Rd.
The request originates from property owner Ali Javed, as documented by Town Board Resolution 400-25 from the Town of Mount Pleasant