Parks & Environment
1.
CBA-RP056-Playland Infrastructure, Rides and Site Work
Following an arbitration decision, the County owes Standard Amusements LLC $519,294 in remaining interest on liquidated damages
2.
2025 Operating Budget Amendment-RP056-Playland Infrastructure, Rides and Site Work
The amendment reduces capital costs by $27,710,000 and adds interest costs of $519,294, resulting in a net decrease in General Fund expenses and reven...
3.
BOND ACT(Amended)-RP056-Playland Infrastructure, Rides and Site Work
The total estimated maximum cost has been increased from $36,000,000 to $36,519,294